Dunnellon FL Air Conditioning Repair Services
BlueSky Cooling Comfort provides top-of-the-line air conditioning and heating services in Dunnellon, FL, including expert repairs, replacements and maintenance.
Read our Dunnellon, FL reviews to see how our heating and cooling services have met all of the needs of our customers, from emergency AC repairs to detailed HVAC maintenance.
Local Reviews
for Dunnellon, FL
Our Reviews by City
Excellent Service
Gary - Dunnellon, FL 34431
AC went out on Friday evening. Out of 7 companies called that said they offered 24/7 emergency service Chris of Blue Sky is the only one that returned my call. He tried to help me out remotely but parts were necessary. Came over Monday morning to diagnosed the problem and ordered the part and returned to install as soon as they came in. Very polite, professional and efficient. I would highly recommend them!
DunnellonFL34431 29.0925-82.475Chris's awesome performance
David - Dunnellon, FL 34431
We are totally satisfied with Chris's communication, promptness and his work ethic.
DunnellonFL34431 29.055-82.475Totally satisfied!
Dawn - Dunnellon, FL 34431
On the ball, excellent communication with me on when they would arrive and time it would take to install 2 ton unit with air handler. Left no trace. Cleaned work area up. Explain how a thermostat worked and how to take care of the unit. I am completely satisfied and pleased that I chose Bluesky Cooling Comfort.
DunnellonFL34431 29.175-82.515Satisfied!
Andres - Dunnellon, FL 34432
Great Company!, Chris was on time, knowledgeable and honest.
DunnellonFL34432 29.145-82.42Services
Philip - Dunnellon, FL 34431
The guys were very efficient and friendly. Did their job well.
DunnellonFL34431 29.1525-82.555Great service! Very dependable!
Vivian - Dunnellon, FL 34432
DunnellonFL34432 29.0475-82.46
Outstanding professionalism.
Mike - Dunnellon, FL 34432
Awesome experience from start to finish. Chris and his helper were very professional and made the whole process painless. They took time to answer questions during the install. Would highly recommend this company!
DunnellonFL34432 29.0925-82.3475quality service at affordable prices
Mark - Dunnellon, FL 34431
Blue Sky had kept my antique a/c unit going for the last four years with fast professional, courteous service, but my 16 year old system finally kicked the bucket and could no longer be resurrected. Blue Sky Quoted me a quality complete replacement unit at a very fair price. They scheduled me in for the job on a Friday for the work to be done on Monday. Started in the morning Removed the old unit, installed the new unit, cleaned up and took way the old unit. We were up and running By 5:00. Amazing job by Chris and his team.
DunnellonFL34431 29.1425-82.475Excellent Service
Maxine - Dunnellon, FL 34432
Chris was very responsive and explained exactly what needed to be done to replace the existing AC unit. He was able to install the AC unit within a few days during one of the hottest days in Florida. He also was able to drop off a room AC fan to help cool the house while waiting for the AC unit to be installed. It was a pleasure to do business with Chris!
DunnellonFL34432 29.02-82.3075you people are the best the best price
Judith - Dunnellon, FL 34432
I wish every body would have your company for service
DunnellonFL34432 29.0775-82.4375Great Service - sevice tech was great
Bob - Dunnellon, FL 34432
Annual maintenance, fixed system not working.
DunnellonFL34432 29.02-82.31Christopher S.
Customer reported no cool. Scheduled SAME day appointment. Upon arrival found system in alarm mode. Compressor. Found defective dual capacitor. Removed defective part. Installed new capacitor. Started system and checked all amperages. Each within manufacturer’s specifications. system running again
Christopher S.
Gabriel S.
Bluesky Cooling Installed high-efficiency AC units in my home. I have a 16 SEER 4 Ton and a 16 SEER 2.5 Ton Heat Pump. These units are designed to provide efficient cooling and heating, helping me reduce my energy bills and improve the comfort of my home.
Christopher S.
Customer reported no cool. Upon arrival found defective transformer that was replaced. Once new transformer was installed the control fuse blew out. After further troubleshooting found defective reversing valve solenoid had failed. We ordered the new part. Returned the next day and installed new part. Tested operation. The system is now operating properly.
Christopher S.
Customer approved proposal to replace three systems. With Daikin systems. Upon installation removed original systems. Removed defective air handler deck and defective return plenum on 4 ton system. Fabricated new return air plenum and installed. Added support before installing new air handler deck. Removed UV light to reuse on new system. Installed new air handlers, heaters, float switches, thermostats and condensers. Transitioned new air handler to existing supply duct. Nitrogen purged lines during soldering process. Pressure tested lines. Pressures held. Evacuated system. Wired up each system and thermostat. Started and checked operation. Systems running as per manufacturers specifications.
Christopher S.
Customer reported two ton unit compressor not starting. Scheduled next day appointment. Upon arrival checked compressor for ground and for short circuit. None found. Checked capacitor. The capacitor was within range. Started compressor. Compressor drew lock rotor amperage. Indicating Defective compressor. Placed order under warranty with TRANE 2/10/2023 Picked up new compressor at local TRANE distributor. Returned to property. Recovered refrigerant. Removed defective compressor. Installed new compressor. Pressure tested OK. Evacuated system. Charged system with recovered refrigerant. Reconnected electrical to compressor. Restored power to system. Started system and checked operation. Adjusted refrigerant levels. System operating properly.
Christopher S.
Performed scheduled maintenance. As part of maintenance, blew out drain line and treated with algicide tablets. Checked operation in cool and fan modes. Checked temperatures, amperages and electrical. All within manufacture’s specifications. Replaced electrical connection in heat pump condenser, found filter clean.
Christopher S.
System only running in heat mode. Found defective thermostat. Ordered new one thermostat under warranty. Returned and replaced. System running in all modes.
Gabriel S.
Problem - Found no low voltage. Determined system had a defective transformer. Replaced Transform and added a low voltage control fuse. When tested again newly installed fuse blew. Found heater contactor shorted. Removed and installed new contactor. Restored power and checked operation. System operating properly at this time.
Christopher S.
Installed new 4.0 Ton Heat Pump Package unit (14 S.E.E.R) Air conditioning system. As part of the install recovered refrigerant and removed original equipment. Installed new return air plenum stand, media filter, air handler, heater, heat pump condenser, float switch and thermostat and tie downs. Wired in electrical. Transitioned new air handler into existing supply plenum. Brazed refrigerant lines and pressure tested system. Leak checked. Evacuated system. opened isolation valves and started system. Checked operation in heat, cool and fan modes. Started system and operating to manufactures specifications. Registered for equipment warranty and left permit with homeowner for purposes of inspection.
Christopher S.
New Air Conditioning System installation. As part of installation added new air handler deck. New air handler, filter rack, heater, float switch, thermostat, hurricane pad and heat pump condenser. After Installation pressure tested new connections, Evacuated system. Opened isolation valves and started system. Checked operation. System operating to manufacturer’s specifications. Requested and delivered extended mfr. warranty.
Christopher S.
Customer reported no cool. Performed Coil cleaning. System performing ok
Christopher S.
Installed new Heat Pump System (AC). Included applying for permit, removing and disposing of old equipment testing and insuring new system working properly
Christopher S.
Installed new Heat Pump System (AC). Included applying for permit, removing and disposing of old equipment testing and insuring new system working properly
Christopher S.
Installed new American Standard Air Conditioning System. Removed, rebuilt and reinsulated Air handler plenum due to poor condition. Installed new air handler, heater and line chase. Leveled area around original pad for new hurricane pad. Returned following day and installed new copper line set and, pad and heat pump condenser. Secured heat pump condenser to new pad. Pressure tested new connection. Pressures held. Installed new programmable thermostat. Started system and checked operation. Operating to manufacturer’s specifications. Registered equipment.
Christopher S.
Installed 2.5 ton mini split system. After consulting with owner about location of new mini split fan coils. Measured and cut openings for new mini split systems. Installed new ceiling mounted cassette fan coils and wall mounted fan coil. Installed new copper line sets and line covers. Installed hurricane pad and heat pump mini split condenser. Secured heat pump condenser to hurricane pad. Tied in copper. Pressure tested overnight. Pressures held. Evacuated system. Open isolation valves. Tied in high and low voltage electrical. Started system and checked operation. Removed original air handler and condenser.
Christopher S.
Installed new Air Condition system. Removed original equipment. Flushed existing copper line set. Reinforced air handler deck with supports. Repaired return air plenum. Installed new air handler deck, air handler, heat pump condenser, heater, float switch, pad and tie downs. Started system and checked operation. Operating to manufacturer’s specifications.
Christopher S.
Installed new Air Conditioning System. Removed original equipment and nitrogen flushed existing copper line set. Removed air handler deck. Inspected return plenum. OK. Installed new air handler deck with support legs. Installed air handle r, filter rack, hurricane pad, heat pump condenser, heater, float switch and thermostat. Brazed all lines while nitrogen purging. Pressure tested. Held pressure. Evacuated system. Wired in new system. Started system and checked operation. Operating to manufacturer’s specifications.
Christopher S.
Installed Customer three ton Air Condition System Removed original equipment. Installed air handler on existing filter rack, hurricane pad, heat pump condenser, heater, float switch and thermostat. Brazed all lines Pressure tested. Wired in new system. Started system and checked operation. Operating to manufacturer’s specifications. Deliver extended warranty and permit.
Gabriel S.
New Air Conditioning Installation - As part of installation - removed defective system. Installed new hurricane pad, straight cool condenser, tie downs, custom galvanized air handler plenum, air handler, heater and float switches. Installed new copper line set. Nitrogen purged copper lines during soldering process. Pressure tested system. Pressures held. Evacuated line set. Ran new high voltage wires from panel to new air handler. Electrically connected system to high and low voltage. Started system and checked operation. Operating to manufactures specifications.
Gabriel S.
Installed new Air Conditioning System - As part of installation removed defective system. Installed new hurricane pad, heat pump condenser and tie downs. Repaired air handler deck and added support. Installed air handler, heater and float switch and thermostat. Flushed existing copper line set. Nitrogen purged copper lines during soldering process. Pressure tested system. Pressures held. Evacuated line set. Electrically connected system to high and low voltage. Started system and checked operation. Performing to manufactures specifications
Christopher S.
Air Conditioner Service. Customer approved AC blower motor replacement. Ordered new blower motor and scheduled next day installation. Picked up new blower motor from supplier. Returned to home and removed defective motor. Installed new motor. Wired power to motor. Started motor and checked operation. Operating to manufacturer’s specifications. Customer requested maintenance be performed. Blew out drain line, treated with algaecide tablets, checked temperature split, amperages and pressures. Washed down condenser with water. Recommended that air handler breaker be replaced. Not setting on each throw.
Christopher S.
Customer reported outside AC Condenser unit noisy. Scheduled next day service. Upon arrival found condenser motor bearing seized up. Removed defective motor and installed new condenser motor. Wired in new motor. Started unit and checked operation of new motor. Operating properly. House started to cool down.
Christopher S.
Customer approved proposal for new AC system. Ordered equipment, Applied for permit and scheduled installation date. Upon arrival recovered refrigerant from existing Air Conditioning system. Removed original equipment. Nitrogen flushed and R11 flushed existing copper line set. Installed new air handler deck, air handler, heat pump condenser, heater, float switch, thermostat and hurricane condenser pad. Brazed all lines while nitrogen purging. Pressure tested. Held pressure. Evacuated system. Wired in new system. Started system and checked operation. Operating to manufacturer’s specifications.
Christopher S.
Customer requested service AC not cooling Found defective capacitor. Replaced and system began to cool.